Forestry
Case Study #1

Case Study No.: 10100018
Application: Smart Gates / Spreader Chains
Cost Savings: $20,142

These drives are high-speed applications that cannot be adequately lubricated due to excessive speeds which results in accelerated elongation. On average, the competitor’s chain was being replaced approximately every 2 months or 60 days. After replacing it with Tsubaki’s Speed Master chain with hard chrome plated pins the customer experienced approximately 14 months or 420 days without any downtime or maintenance. The hard surface over the pin prolongs the elongation period, thus, keeping critical drives lasting longer.